Ratio and proportion - Grade 5 (Question: 1604462417) Locked
If 9 men can do a piece of work in 12 days, how many men can do it in 4 days at the same rate?
A. 6 men
B. 5 men
C. 27 men
D. 30 men
If 9 men can do a piece of work in 12 days, how many men can do it in 4 days at the same rate?
A. 6 men
B. 5 men
C. 27 men
D. 30 men