Direct and Inverse Proportions - Grade 8 (Question: 1613051083) Locked
A man completes \({2 \over 5}\) of a job in 14 days. At this rate, how many more days will it take him to finish the job?
A. 31 days
B. 21 days
C. 18 days
D. 22 days